How to review open variations before an Abu Dhabi project cost meeting
A revised lobby layout arrives just before the monthly cost meeting on an Abu Dhabi office project. The partition contractor has priced the change, the electrical contractor is still measuring it, and the client has agreed neither figure. What amount should the project director carry into the forecast?
Give each figure a meaning
Start the open variation review with the source of the change. Identify the instruction or drawing, the affected area and the basis of each estimate. For example, a partition quotation of AED 40,000 and an electrical allowance of AED 10,000 give the team a working estimate of AED 50,000. Label the allowance explicitly so a reader can see which part still needs pricing.
Update the forecast when evidence changes
If the electrician later quotes AED 8,000 for the same scope, replace the AED 10,000 allowance. The revised estimate is AED 48,000. Adding the quotation to the previous total would count the electrical work twice. Keep the calculation and its date with the supporting quotations so the next reviewer can explain the change.
Fortis Sync Variations holds the source instruction, supporting documents, cost impact and approval history together. A commercial manager can review open and agreed values by package and use the underlying record to explain an individual movement.
End with a decision and an owner
Ask the quantity surveyor to confirm whether both quotations cover the same drawing revision. Ask the planner which activity the change affects. Give the named reviewer a date to return the valuation under the project’s approval process. Carry the amount as open until the appropriate approval is recorded.
For the director, the most useful line in the meeting pack now reads: lobby layout change, AED 48,000 estimated, electrical quotation received, scope check due Thursday. The figure has a basis, and the team knows what could change it next.
Keep reading
More from Fortis Sync

Which drawing goes to site? A revision check for Dubai fit-out teams
On a Dubai apartment fit-out, a supervisor has marked the bathroom door opening from a printed plan. The joinery contractor has a…
Read more
Before the ceiling closes: a 360° capture route for Dubai MEP teams
When a ceiling contractor asks which bays can close tonight, a folder of site photographs can leave the MEP coordinator with an…
Read more
How Abu Dhabi project teams can close procurement actions in weekly meetings
“Supplier to follow up” can survive several sets of meeting minutes while the installation date gets closer. A procurement action review gives…
Read more